The permit is the document that makes hot work permitted. Whoever issues it has walked the place, decided which precautions are required and written them down, and in doing so has taken a position: that this work can be carried out safely, there, then. It is a role with real content, which is why it belongs to whoever controls the premises rather than to whoever does the work.
What the permit has to answer
- Which work is to be done, where, and for what period the permit is valid.
- Who carries out the work and who watches it — by name, not by job title.
- Which combustible materials and spaces are nearby, including behind and beneath the work.
- Which precautions have to be in place before the work starts.
- Which extinguishing equipment must be at hand, and where the alarm route runs.
- How long the after-watch is to last.
How a permit is issued
- 1
Confirm the role is yours
The permit issuer is appointed by whoever controls the worksite. If you hire a contractor, the role still sits with you unless you have expressly agreed otherwise in writing.
- 2
Walk the site with the person who will work
The risk assessment is made on site, not at a desk. The person who is going to weld knows where the sparks land; the person who owns the building knows what is behind the wall. Neither manages the assessment alone.
- 3
Decide the precautions before writing them
The form is a checklist, not a risk assessment. Ticking a box about covering before anyone has looked at what needs covering is the commonest way to make a correctly completed permit worthless.
- 4
Sign it and hand it over
The permit has to be on site during the work, so whoever is watching can read what applies. A permit in a binder at the office governs nothing.
- 5
Follow up that it was closed out
The after-watch is part of the permit. Whoever issued it has reason to know it was carried out, since it was their assessment that said how long it should be.

Buying in the work does not move the responsibility
This is the most expensive misunderstanding on the page. A client who hires a contractor for hot work often assumes the certificates, the permit and the watch are all included in the price. The certificates are. The permit is not: it is issued by whoever controls the place, because they are the ones who know what is behind the walls. If it goes wrong, that assessment is what gets examined.
Questions about permits
- Can we appoint a permit issuer who sits at head office?
- In practice, no. The role requires an assessment of the place, and that cannot be made remotely. With several sites you need somebody appointed and certified at each of them.
- How long is a permit valid?
- For as long as it says, and for the work it names. New work in the same place is a new permit, even if the same person does it the next day, because conditions may have changed in between.
- Does the permit issuer need the same course as the operative?
- Yes, it is the same certification course. It is built so that all three roles understand each other's duties, which is the whole point: the permit is written by somebody who knows what the watch can actually see.
Appointing permit issuers at several sites?
Tell us how many places it covers and we will say how to get it done in one go rather than one at a time.
Contact us